Click on the number to view progress.

Note:
-
Please refer to Figure 1 for the locations of Items 1 to 8 above.
-
The overall progress is as of 28 February 2006.
-
Tuah, the first TBM started boring activity mid June 2004 and broke through at the North Junction Box on 11 December 2004 and boring activity restarted on March 05. Tuah has covered 2565m so far.
-
Gemilang, the second TBM started boring end August 2004 and broke through at South Junction Box on 4 June 2005. Gemilang has re-commenced its journey towards the south and has covered 3790m in distance.