Click on the number to view progress.

Note:
- Please refer to Figure 1 for the locations of
Items 1 to 8 above.
-
The overall progress is 61.7%
as of 30 September, 2005
-
Tuah, the first TBM started boring
activity mid June 2004 and broke through at the
North Junction Box on 11 December 2004 and boring
activity restarted on March 05. Tuah has covered
2135m so far.
-
Gemilang, the second TBM started
boring end August 2004 and broke through at South
Junction Box on 4 June 2005. Gemilang has re-commenced
its journey towards the south and has covered
2340m in distance.
|