Special Report




 


 
| Progress as at 31/8/04
 
Excavation and strutting at cofferdam in progress
Rock blasting work at North Junction Box completed
TBM boring at North Drive and TBM assembly at South Drive in progress
     
TBM boring in progress
Tunnel lining segments being transported into TBM
Assembly of TBM shield segments and Back-up Gantry in progress
     
Hacking recesses for TBM launching thrust frame in progress
Installation of external pipework into slurry treatment plant in progress
Installation of conveyor belt for excavated materials in progress
     
Rock blasting and slope stabilisation works in progress
Structural works at bifurcation (KL Bound) in progress
Structural works (KL Bound) in progress
     
Base slab in progress
Excavation and sheet piling in progress
Construction of wall and top slab in progress
     
 








 
 

 